a person can do a job in 6 day days . another can do the same job in 4days . if they work together, how long do they need to finish the job?

Respuesta :

wegnerkolmp2741o
wegnerkolmp2741o wegnerkolmp2741o
  • 01-08-2020

Answer:

It will take them 2 2/5 days working together

Step-by-step explanation:

To find the time worked

1/a + 1/b = 1/t

Where a and b are the times worked individually and t is the time worked together

1/4 + 1/6 = 1/t

Multiply each side by 12t to clear the fractions

12t( 1/4 + 1/6 = 1/t)

3t + 2t =12

Combine like terms

5t = 12

Divide by 5

t = 12/5

t = 2 2/5

It will take them 2 2/5 days working together

Answer Link

Otras preguntas

Que colores hay en el arco iris?
Why do you need two ammonium ions and one sulfide ion for the formula for ammonium sulfide?
{35 POINTS)What are the solutions of 2a^3-3a^2=8a-12 ?
One group of students uses different methods to conserve water in the garden as listed below. Method 1: Water the garden when the sun is out. Method 2: Water th
In which orbital does an electron in a bromine atom experience the greatest effective nuclear charge?
Explain please thanks
Select all that apply. Which of the following statements are true of the greatest common factor of two numbers? A. Each number must share the factor. B. Th
SIMPLIFY THIS EQUATION! a³ b¹⁰ ------ a² b²
How can you tell the difference between a terminating decimal and a repeating decimal?
2(v-h)/k=r Solve equation for v in terms of all other variables involved