Is typically not referred to as a buffer type in critical chain project management?

Respuesta :

dinosaurbarn
dinosaurbarn dinosaurbarn
  • 14-01-2018

The answer is Free Buffer. Project buffer, a not usual and the only one buffer to protect the project deadline;

Feeding buffer it is different types of buffers to protect parts of the critical chain. And resource buffer is a multiple artificial buffers that act as warning signals to assure that it is available of resources.

Answer Link

Otras preguntas

Which answer is the correct way to fix the following sentence? Slipping on the wet sidewalk, the keys fell from Amaury’s pocket.
In 1938 britain and france attempted to ________________ nazi germany
Robert took a math test and got 36 correct and 14 incorrect answers. What was the percentage of correct answers? 72% 28% 50% 36%
What discovery was made by Robert Hooke in 1665
why might the Persian empire have posed a danger to greece
5 matching French questions?
The text book defines human development as "the scientific study of the changes that occur in people as they age from conception to death. the lecture leaves ou
The dutch claim in the new world was established at _______.
What is the transfer of energy by electromagnetic waves? A) radiation B) conduction C) convection D) thermal energy
What kind of rock is created when magma cannot escape the crust and instead cools and hardens in the crust? Question 2 options: Sedimentary Rocks Metamorphic Ro