Three workers can do a job in 28 hours. How many more workers are needed to do this job in 12 hours?

Respuesta :

MrRamon
MrRamon MrRamon
  • 13-04-2018
4 additional workers for 7 total workers.
if it takes 3 workers 28 hours to do work there are 84 total hours of work (3*28=84) to find how many workers it will take to get the work done in 12 hours divide 84 by 12. 84/12= 7 total workers. 7-3= 4 additional workers needed.
Answer Link
pranilraichura
pranilraichura pranilraichura
  • 08-03-2020

Answer:

4 workers

Step-by-step explanation:

Answer Link

Otras preguntas

who's this president?
If m <AVC= (9x-20)° and m AC =86°, find the value of x
the last step in a proof contains the
Which two empires split because of world war 1-the ottoman empire -the russian empire -the austro-hungarian empire-the french empire -the british empire?
Read the passage from Hamlet, Act I, Scene iii. Laertes: For he himself is subject to his birth; He may not, as unvalu’d persons do, Carve for himself, for on
Find the exact value of sin(60-45)
There is only one possible path for each stage in the rock cycle. Please select the best answer from the choices provided T F
Pls help me guys! This is super hard
Which sentence is written correctly? My father talks less than anyone in our family. Her dress was prettier than all the dresses. No one can be as charming as m
whats this painting called??? and is there something wrong with the baby in the painting